The Centre for Mathematical Sciences has been undergoing a refurbishment of its offices, common areas, meeting rooms and lecture theatres since November 2023
What has been happening during the refurb?
The main part of the project has involved an electrical upgrade of the light fittings throughout the site to LEDs. The lighting in offices are also being switched over to PIR settings so both of these upgrades will ensure we are being more ecological with our electricity usage. The woollen carpets throughout the buildings are being replaced with floor tiles allowing easy replacement when necessary and all the painted surfaces are getting a fresh coat of paint. Also you will notice that the kitchens in the Common Rooms have been completely renewed and Pavilions D & G have had dishwashers installed to be used by Facilities for events.
We are now in the last Pavilion (Pav E) and this is very nearly finished. Accessibility to ground floor offices and the Common Room should be week commencing 8th December 2025. This will be confirmed nearer the date.
BLACK PACKING BOXES
IF YOU STILL HAVE ANY PACKING BOXES USED IN THE REFURBISHMENT YOU HAVE UNTIL 16 JANUARY 2026 TO UNPACK AND MAKE THESE BOXES AVAILABLE FOR PICK UP BY FACILITIES.
MOVING OUT DATES - For Pav E
| Floor | Moving Out Date | Moving In Date |
| 2nd Floor | complete | |
| 1st Floor | complete | |
|
Ground Floor |
complete | 8 December (TBC) |
What is happening over the Christmas 2025 Break
- MR3 will be the last of the main lecture theatres to get its update
- Pavilion A will get the new carpet tiles once the scaffolding has been taken down from the roofing project